NRG Discusses Texas Expansion That Could Support 2.4 GW of Data Demand

Image: TokenPost
NRG Energy is discussing an expansion of its Texas data center power arrangement that could support as much as 2.4 gigawatts of customer demand, up from the 1.2-GW plan now in place. The talks involve the unnamed cloud and AI hyperscaler tied to the project. The 2.4-GW figure describes potential demand at the same location; an expansion agreement has not been completed. NRG announced the initial project Aug. 4 through its Bring Your Own Power (BYOP) initiative, which pairs a data center with dedicated generation. The planned combined-cycle gas plant is expected to begin operating in late 2029. Its contract is set to run for at least 15 years and is backed by an investment-grade guarantee. NRG expects the project to cost $3.2 billion.
Read the full story on TokenPostBeCrypto News shows a short excerpt and links to the publisher. The full report belongs to TokenPost.